College Databases Annual Plan 2018-19

Here are the projects we have lined up for the coming academic year: Summer 2018 through Spring 2019. We have ...
Read More

Cycle 101

4/1/2019 - 4/12/2019 Work Complete Applicant Review When an Application is deleted system checks if that Application was only reference ...
Read More

Cycle 100

3/18/2019 - 3/29/2019 Work Complete Work continues toward Deleting Application Data. This cycle I implemented some tools to help Institutional ...
Read More

Cycle 99

3/4/2019 - 3/15/2019 Work Complete Applicant Review This cycle was focused on building out our Application Data Warehouse data set ...
Read More

Cycle 98

2/29/2019 -- 3/1/2019 Work Complete Appreview (90%, awaiting owner approval) Add Decline Note to Applicant Review detail page. This is ...
Read More

Cycle 97

2/4/2019 - 2/15/2019 Work Complete Courses Changed the definition of "Evening Class" to courses that start at 4:30 PM or ...
Read More

Cycle 96

1/22/2019 - 2/1/2019 Work Complete Hiring (Complete) New header and menu. Move menu button to far left and W logo ...
Read More

Cycle 95

12/27/2018 - 1/18/2019 Work Complete Applicant Review (Complete) Displays applicant preferred name entered in MyGrad application. (If there is conflicting ...
Read More

Cycle 94

12/10/2018 - 12/21/2018 Work Complete Appreview (Complete) Bookmark note length is extended to 100 characters. When user enters more than ...
Read More

Cycle 93

11/27/2018 - 12/7/2018 Work Complete Hiring (Complete) Add a Workday Revisit Date. HR has the option to add a Revisit ...
Read More

Cycle 92

11/13/2018 - 11/20/2018 This cycle we did some tuning on the Hiring Database (NARF) in preparation for broader implementation in ...
Read More

Cycle 91

10/29/2018 - 11/9/2018 Work Complete Appreview (Fixed) Save and Delete buttons were not being displayed in modal windows in Rubric ...
Read More

Cycle 90

10/15/2018 - 10/26/2018 Work Complete Applicant Review (Complete) Personal application bookmarks can be removed from the bookmark list view. Expanded ...
Read More

Cycle 89

9/24/2018 - 10/12/2018 Work Complete Applicant Review (90% Complete) Personal application bookmarks in applicant review allow a reviewer to mark ...
Read More

Cycle 88

9/4/2018 - 9/21/2018 Work Complete We wrapped up and deployed the 2018 Rubric Refresh. User visible changes are highlighted below ...
Read More

Cycle 86

8/13/2018 - 8/24/2018 Work Complete Appreview (25% complete) Working on 2018 Rubric Refresh. (Complete) Undergraduate application processing checklists. Add workflow ...
Read More

2018 Rubric Refresh

I will be working on some backlog projects for the Rubric system in Applicant Review during Summer Quarter 2018. Project ...
Read More

College Databases Annual Plan 2018-19

Here are the projects we have lined up for the coming academic year: Summer 2018 through Spring 2019. We have ...
Read More

Cycle 85

Jul 30 - Aug 10, 2018 Work Complete Courses (Complete) Show both actual enrollment and projected enrollment on all offerings ...
Read More

Cycle 84

July 16, 2018 through July 27, 2018 Work Planned My next major project this summer will be revisiting the Rubric ...
Read More

Cycle 83

July 7 - July 13, 2018 Work Complete Appreview (Fixed) Needs Advisor list was not displaying the newly selected advisor ...
Read More