12/31/2019 Last few weeks have include substantial work on Placement data in the college Student database. I've also been doing ...

Cycle 109

10/21/2019 - 11/1/2019 Work Complete Applicant Review (Done) Button to import ACT/SAT scores from central UW SDB. Our bulk import ...

Cycle 108

10/7/2019 - 10/18/2019 Work Complete Applicant Review (Complete) Add Delete Preview report. This report show the applications that are queued ...

Cycle 107

9/23/2019 - 10/4/2019 Work Complete Applicant Review (Complete) Add a Certification tracking report in Applicant Review. This report shows the ...

Cycle 105

Through 7/10/2019 Work Complete This is a catch-up post for several weeks worth of work. During the end of the ...

Cycle 104

5/13/2019 - 5/25/2019 Work Complete Appreview (Complete) Update report filter "Period" to only show years and quarters where applications exist ...

Cycle 103

Apr 29, 2019 - May 10, 2019 Work Complete Applicant Review (Complete) Finalized delete time frame as 3 quarters after ...

Cycle 102

4/15/2019 - 4/26/2019 Work Complete Applicant Review (Complete) Delete Character & Fitness forms. These are forms formerly collected by the ...

Cycle 101

4/1/2019 - 4/12/2019 Work Complete Applicant Review When an Application is deleted system checks if that Application was only reference ...

Cycle 100

3/18/2019 - 3/29/2019 Work Complete Work continues toward Deleting Application Data. This cycle I implemented some tools to help Institutional ...

Cycle 99

3/4/2019 - 3/15/2019 Work Complete Applicant Review This cycle was focused on building out our Application Data Warehouse data set ...

Cycle 98

2/29/2019 -- 3/1/2019 Work Complete Appreview (90%, awaiting owner approval) Add Decline Note to Applicant Review detail page. This is ...

Cycle 97

2/4/2019 - 2/15/2019 Work Complete Courses Changed the definition of "Evening Class" to courses that start at 4:30 PM or ...

Cycle 96

1/22/2019 - 2/1/2019 Work Complete Hiring (Complete) New header and menu. Move menu button to far left and W logo ...

Cycle 95

12/27/2018 - 1/18/2019 Work Complete Applicant Review (Complete) Displays applicant preferred name entered in MyGrad application. (If there is conflicting ...

Cycle 94

12/10/2018 - 12/21/2018 Work Complete Appreview (Complete) Bookmark note length is extended to 100 characters. When user enters more than ...

Cycle 93

11/27/2018 - 12/7/2018 Work Complete Hiring (Complete) Add a Workday Revisit Date. HR has the option to add a Revisit ...

Cycle 92

11/13/2018 - 11/20/2018 This cycle we did some tuning on the Hiring Database (NARF) in preparation for broader implementation in ...

Cycle 91

10/29/2018 - 11/9/2018 Work Complete Appreview (Fixed) Save and Delete buttons were not being displayed in modal windows in Rubric ...

Cycle 90

10/15/2018 - 10/26/2018 Work Complete Applicant Review (Complete) Personal application bookmarks can be removed from the bookmark list view. Expanded ...